Key Highlights
● Highest ever quarterly Total Income and EBITDA reported by the Company
● EBITDA margin expanded to 91.36% in Q2 FY27 from 81.02% in Q2 FY26
● Cash PAT# rose 3.9-fold YoY to INR 152.55 Cr
● Commissioned 1,036 MWp of new RE capacity and ~503 MWh of BESS in the first seven months of FY27
● Commissioned 51 units of India’s largest wind turbine by rotor diameter (5 MW, 181 m rotor) in FY27 till date
● Total operational capacity reached to 2,844 MWp of renewable energy + 604 MWh of BESS, as on date
● Targeting BESS installation of ~4,500 MWh by June 2027 and ~10,000 MWh by March 2028
● Total capex incurred till September 30, 2026 of INR 18,895 Cr, including capex of INR 2,591 Cr in Q2 FY27
● ICRA upgraded the credit rating of Juniper Green Energy Limited to AA- (Stable)

Portfolio Overview
● Total portfolio as on date of 11,218 MWp , along with 8,989 MWh of BESS capacity
● 98% of the portfolio is with off takers rated ‘A’ or above;
● 98% of the portfolio is secured through long-term PPAs, typically of 25 years
● Connectivity secured, granted and/or applied for the full portfolio, with surplus connectivity of over 5,200 MW available for future bids and connectivity available for installation of more than 20,000 MWh of BESS